This line serves as a static benchmark to assess delays or advances in
execution.
Definition:
Captures the real execution status based on actual completion of tasks.
Calculation Logic:
- Grand total of Actual % of nth level activities. Actual end date is used to sum by month.
Example from Graph:
As
of June 17 2025, actual progress is 71.29%.
This
indicates that although the baseline expected 90% by May 25, only 71.29%
was truly completed by mid-June.
Purpose:
This shows the real work completed, regardless of planned or baseline
timelines.
3. Forecast Progress (%)
Definition:
Estimates how much work should be completed, based on the current
project plan and any re-forecasting.
Calculation Logic:
- Grant total of Planned % of Deliverable Groups. Planned End Date is used to sum by month.
Example from Graph:
On Aug
2025, forecast progress is 96.36%.
This
suggests that based on the latest revised schedule, 96.36% completion is
expected by that date.
Compare
this to actuals: if actuals lag behind, it shows potential risk.
Purpose:
Forecast is a dynamic guide, adapting with replanning or updated
timelines.
Summary Table
|
Progress Type
|
Source Date Field
|
Level of Calculation
|
Graph Example
|
|
Baseline
|
Baseline End
Date
|
Deliverable Group (5th Level)
|
90% on May,
2025
|
|
Actual
|
Actual End
Date
|
Task Level
(Nth)
|
71.29% on June
17, 2025
|
|
Forecast
|
Planned End
Date
|
Deliverable
Group (5th Level)
|
96.36% on Aug
2025
|