Understanding Project Progress in KTern.AI: Baseline vs Actual vs Forecast
In KTern.AI, project progress tracking is anchored in
structured, date-based logic, visualized through trends like the one shown
below. This graph helps compare how the project is performing against what was
planned (baseline) and what is currently expected (forecast). Here’s how each
metric is defined and calculated, with examples from the graph.

1. Baseline Progress (%)
Definition:
Represents the original committed progress based on the baseline end dates
defined during planning.
Calculation Logic:
- Grant total of Baseline % of Deliverable Group Level. Baseline End Date is used to sum by month.
- Note:
- Baseline % values are provided by the Motiva Kaar PMO team post approval from the Motiva PQL team.
Example from Graph:
On May
2025, baseline progress reaches 90.00%.
This
means that, according to the original plan, 90% of the project should have
been completed by then.
Purpose:
This line serves as a static benchmark to assess delays or advances in
execution.
2. Actual Progress (%)
Definition:
Captures the real execution status based on actual completion of tasks.
Calculation Logic:
- Grand total of Actual % of nth level activities. Actual end date is used to sum by month.
Example from Graph:
As
of June 17 2025, actual progress is 71.29%.
This
indicates that although the baseline expected 90% by May 25, only 71.29%
was truly completed by mid-June.
Purpose:
This shows the real work completed, regardless of planned or baseline
timelines.
3. Forecast Progress (%)
Definition:
Estimates how much work should be completed, based on the current
project plan and any re-forecasting.
Calculation Logic:
- Grant total of Planned % of Deliverable Groups. Planned End Date is used to sum by month.
Example from Graph:
On Aug
2025, forecast progress is 96.36%.
This
suggests that based on the latest revised schedule, 96.36% completion is
expected by that date.
Compare
this to actuals: if actuals lag behind, it shows potential risk.
Purpose:
Forecast is a dynamic guide, adapting with replanning or updated
timelines.
Summary Table
Progress Type
|
Source Date Field
|
Level of Calculation
|
Graph Example
|
Baseline
|
Baseline End
Date
|
Deliverable Group (5th Level)
|
90% on May,
2025
|
Actual
|
Actual End
Date
|
Task Level
(Nth)
|
71.29% on June
17, 2025
|
Forecast
|
Planned End
Date
|
Deliverable
Group (5th Level)
|
96.36% on Aug
2025
|
Related Articles
How baseline version and metrics are calculated in KTern.AI - Project Planner ?
Project Governance When managing projects, a "baseline" refers to the initial plan approved by key stakeholders, capturing expectations for scope, time, and cost. Tracking baseline metrics such as Baseline Start, Baseline End Date, Baseline Duration, ...
How planned vs actual progress is calculated in PSR ( Program Status Report) Dashboard ?
Introduction: This document provides a comprehensive guide to understanding and interpreting the planned versus actual progress metrics within the PSR Dashboard. This information is crucial for project managers and stakeholders to assess project ...
How Project Planning Can Be Done Effectively Using KTern's Workbook ?
KTern.AI-Workbook provides you with the option of updating your project using the workbook. Timeline is a place where users can add and edit tasks in the auto-generated project plan. The workbook is a view similar to excel sheet where all the tasks ...
How Is Project Progress Calculated In KTern?
In KTern’s Transformation Hub, you can monitor the progress of your projects using dashboard. The dashboard features a progress bar that provides an overview of the project’s advancement from its inception. You can configure the progress calculated ...
How is the "Forecast Actual %" Is Calculated In Planned Vs Actual Graph?
Tracking and comparing the planned Vs actual progress of a project is critical for ensuring timely delivery and efficient resource utilization. However, deviations from the planned timeline often occur due to unforeseen challenges, requiring dynamic ...