Trigger | Scenario | Workflow Raised? | Why? |
Date Change | Edit task dates — cascades to authorized tasks only | No | All affected tasks are within your permission |
Date Change | Edit task dates — cascades to unauthorized tasks | Yes | Other group's tasks are impacted |
Task Addition | Add task affecting parent/dependent task dates | Yes | Structural change impacts other groups |
Task Deletion | Delete task impacting dependent task schedule | Yes | Other group's task dates shift |
Indent/Outdent | Move task causing date shift to any task | Yes | Structural hierarchy change |
Direct Edit | Edit own task with no cascading impact | No | No downstream impact detected |
Locked Task Edit | Try to edit task under pending workflow | Blocked | Data conflict prevention |
Scenario | Authorization | Workflow | Outcome |
Edit own task, no cascading impact | Required | Not triggered | Saved immediately |
Edit own task affecting authorized tasks | Required | Not triggered | Saved immediately |
Edit own task affecting unauthorized tasks | Required | Triggered | Approval needed before saving |
Attempting to edit another user's task | Denied | N/A | Cannot proceed |
Indent/outdent any task affecting dates | Required | Triggered | Approval needed for structural change |
Modify locked task during pending workflow | Blocked | N/A | Must wait for workflow resolution |